Great British Energy chief Dan McGrail disclosed the scale of the early approaches in an interview with EIC CEO Stuart Broadley on the EIC Clearly podcast
Buyers now face four-year lead times for large power transformers, McGrail said.
Aberdeen, 18 August 2026:
Great British Energy had 52GW to 53GW of opportunities in its pipeline when Dan McGrail joined as chief executive, before the publicly owned energy company began engaging with the market, he told Stuart Broadley, CEO of the Energy Industries Council (EIC), in an interview on the EIC Clearly podcast.
McGrail described the figure as approaches from organisations that wanted to work with GB Energy. The company has since set a target to establish a portfolio, through investment and ownership, that will deliver at least 15GW of clean-energy generation and storage capacity.
“When I started, there were about 52, 53 gigawatts of opportunities in our pipeline, which was before we cultivated the market, before we'd been out and started to say, this is what we're going to do,” McGrail said. “People just coming to us and saying, we'd like to work with GB Energy.”
He said GB Energy had to narrow those opportunities to technologies where public investment could have the greatest impact. The company is focusing in part on technologies that have passed the early innovation stage and need projects to prove that they can operate commercially at scale.
“When they get to the point of projects, where the things need to be built to prove it and into that commercialisation phase, absolutely we're in there,” he said.
GB Energy was established in 2024 as a government-owned company, and the Great British Energy Act 2025 put it on a statutory footing. The operationally independent company is headquartered in Aberdeen and can develop, invest in, own, build and operate clean-energy assets.
McGrail said GB Energy’s energy-industry expertise may lead it to assess technical, economic, commercial and legal risks differently from a bank.
“Sometimes you really need that deep understanding to see where something is going to fit into a future energy ecosystem, to be able to form an opinion, a risk positive opinion about it,” he said.
He also drew a boundary around GB Energy’s role. “As a publicly owned body, we shouldn't be investing in things which compete with the private sector,” he said, pointing to gas-fired power stations as an area where private companies already have mature development, ownership and operating capabilities.
Supply-chain constraints are already affecting delivery. McGrail said a large power transformer ordered three years ago could have arrived in about a year. Buyers now face a lead time of about four years.
“If we want to deliver it at the speed we want to, then we need to invest in supply chains,” he said.
McGrail said GB Energy expects about 300 people to be working for the company by 2030. It is onboarding roughly eight people a month, with the vast majority based in Aberdeen.
GB Energy separately aims to fund projects that directly support at least 10,000 jobs by 2030, including skills and locations historically dependent on oil and gas.
The full interview is available on the EIC Clearly podcast page. EIC Clearly is also available through EIC Podcasts on Spotify, Apple Podcasts and Amazon Music, and on YouTube.
** ENDS **
Notes to editors:
The Energy Industries Council brings together over 950 companies from the energy supply chain sector across all industries.
Since 1943, we have evolved to provide up-to-date global market intelligence, unrivalled networking opportunities, and direct engagement with policymakers across regions.
Our members — leading innovators, industry experts, and global thinkers — are at the forefront of the energy transition.
Through our leading events, real-time project data, and policy expertise, we help members capitalise on opportunities and scale their operations globally. Together, we are working towards a more sustainable future.