P&Q has signed a contract with Ocean Winds for the delivery of a transmission project in Poland. P&Q will be responsible for the design, supply, construction, installation and commissioning of a 400/275kV substation and an associated 400kV transmission line.
The assets will connect the 500MW BC-Wind offshore wind farm to the new Choczewo substation. The project is fundamental to strengthen BC-Wind's exporting.
According to P&Q, the company is keen to increase local content in the Polish offshore wind sector and to support the country's overall energy transition targets.