Windar Renewables has selected Iberdrola for the manufacturing of 95 transition pieces for the East Anglia 3 project in the UK. This is the largest amount of this type of foundation ever contracted.
The execution of the order will result in over 2 million hours of work over the course of 23 months, generating 400 job positions. Production is set to start in June this year. 
Iberdrola is expected to carry out production at its bases in Avilés, Spain. The pieces will have a maximum heigh of 20 metres, a diameter of 8 metres and a weight of 300 tonnes.
East Anglia 3 will be built offshore Norfolk and is designed to reach a capacity of 1.4GW. The plant will be able to supply clean energy to 1.3 million homes after it enters operation in 2026.